grid_alternatives, fix related entries and simplify/robustify logic to deal with EPSG 'Geographic3D to GravityRelatedHeight' methods
|
|
Fixes #1867
|
|
This commit is the result of the squashing of rfc4_dev branch in a single
commit. It implements mostly RFC 4 related work.
* Grid handling:
- remove obsolete and presumably unfinished implementation of grid catalog functionality
- all grid functionality is in grids.cpp/.hpp
- vertical and horizontal grid shift: rework to no longer load whole grid into memory
- remove hgrids and vgrids member from PJ structure, and store them in hgridshift/vgridshift/deformation structures
- build systems: add optional libtiff dependency. Must be explicitly disabled if not desired
- add support for horizontal and vertical grids in GeoTIFF, if libtiff is available
- add GenericShiftGridSet and GenericShiftGrid classes, relying on TIFF grids, that can be used for generic purpose grid-based adjustment
- add a +proj=xyzgridshift method to perform geocentric translation by grid. Used for French NTF to RGF93 transformation using gr3df97a.tif grid
- deformation: add support for +grids= for GeoTIFF grids
- horizontal grid shift: fix failures on points slightly outside a subgrid (fixes #209)
* File management:
- add a filemanager.cpp/.hpp to deal with file related work
- test for legacy proj_api.h fileapi
- proj.h: add proj_context_set_fileapi() and proj_context_set_sqlite3_vfs_name() (fixes #866)
- add capability to read resource files from the user writable directory
* Network access:
- build systems: add optional curl dependency
- add a curl-based default implementation for network related functionality
- proj.h: add C API to control network functionality, and optionaly provide network callbacks
- add data/proj.ini with default settings
- add a SQLite3 local cache of downloaded chunks
- add proj_is_download_needed() and proj_download_file()
* Use Win32 Unicode APIs and expect all strings to be UTF-8 (fixes #1765)
For backward compatibility, if PROJ_LIB content is found to be not UTF-8 or
pointing to a non existing directory, then an attempt at interpretating it
in the ANSI page encoding is done.
proj_context_set_search_paths() now assumes strings to be in UTF-8, and
functions returning paths will also return values in UTF-8.
|
|
filename substitution
|
|
|
|
|
|
(fixes #1801)
Fix for
```
projinfo --identify "+proj=utm +zone=48 +a=6377276.345 +b=6356075.41314024 +towgs84=198,881,317,0,0,0,0 +units=m +no_defs +type=crs"
```
to only return BoundCRS of EPSG:3148: 70 %
Previously it also returned EPSG:23948 and EPSG:24048 whose projected CRS-only
parts where likely matches, but those 2 CRSs don't have a +towgs84=198,881,317,0,0,0,0,
so discard them.
|
|
aggressive (refs #1787)
'EPSG:1304, Indian 1975 to WGS 84 (2), 5.0 m, Thailand - onshore and Gulf of Thailand'
was removed because considered useless w.r.t first result
'EPSG:1812, Indian 1975 to WGS 84 (4), 3.0 m, Thailand - onshore'
However the name of the area of use is not completely the same, so might be worth
keeping it.
|
|
|
|
that suddenly warns about them for unknown reason...
|
|
Related to https://github.com/OSGeo/proj-datumgrid/pull/66
Tune operation search so that it can work with Geog2D <--> VertCS for commandline
niceness
|
|
Relates to https://github.com/OSGeo/proj-datumgrid/pull/65 ,
https://github.com/OSGeo/proj-datumgrid/issues/22
As EPSG has no entry for it, we create a grid_transformation, as well as a
dedicated area of use based on the extent of the grid, under the PROJ authority.
With the hope to be able to remove it once EPSG has an entry...
|
|
operation that involves a vertical axis reversal
|
|
8a5740637760f837c9145c72ad8080927a3a4bf0 in the no-grid scenario
|
|
not instantiable, allow using through intermediates. Should help in theory for Auckland 46 -> NZVD2016 the case but there are other issues
|
|
CRS and Projected CRS
|
|
createOperations(): optimize compoundCRS to geogCRS, when the geogCRS of the compoundCRS is the same as the target geogCRS
|
|
Add proj_create_derived_geographic_crs() and proj_create_conversion_pole_rotation_grib_convention() to address GRIB datasets using a pole rotation method
|
|
|
|
compoundCRS is the same as the target geogCRS
|
|
overriding CRS on a InverseCoordinateOperation (could be related to #1736)
|
|
proj_create_conversion_pole_rotation_grib_convention() to address GRIB datasets using a pole rotation method
|
|
|
|
intermediates B and C, such there's a A->B operation and C->D operation, and A and C are not exactly the same CRS but use the same geodetic datum
|
|
result through ITRF2008. Was broken in master by the addition of the 'WGS84 -> WGS 84 (Gxxx)' null operations in the PROJ authority
|
|
intermediate CRS if we found direct transformation(s) but had to eliminate them due to other criteria
|
|
distinguish null transform from ballpark transform
|
|
This was introduced in 63857c92b271bbcd10df0a032304982011acb2a9. Due to
the fix done in the previous commit, we can mostly revert the above commit.
We just keep the added tests and the custom WGS 84<-->WGS 84 (Gxxxx) null
transformations.
|
|
operations that belong to different authorities. Should make the concept of geodetic_datum_preferred_hub introduced some time ago obsolete
|
|
|
|
correctly the geographic coordinates of the input coord when the CRS is not Greenwich based
|
|
+geoidgrids and +vunits != m
|
|
|
|
geog2D transformation to a geog3D
Fixes for example EPSG:4979 to EPSG:2189, as raised in
https://github.com/OSGeo/gdal/issues/1972#issuecomment-548814354
|
|
Better filtering based on extent and performance improvements
|
|
a proj_create_vertical_crs_ex()
|
|
|
|
rouault/improve_transformation_with_alternative_vertical_unit_and_direction
Improve transformations with alternative vertical unit and direction
|
|
are missing, especially for compound CRS. Helps having shorter/more relevant results
|
|
functional changes
|
|
This is invalid WKT, but GDAL 2.4 used to accept it and make a reasonable
use of it...
Currently we default it to 0 which is non sensical. Better use 1 as GDAL 2.4
did, and emit a warning.
Other fix: proj_create_from_wkt() was documented to operate by default in
non-strict validation mode, but it was actually in strict mode. So do as
documented.
|
|
Height Depth Reversal and use it in createOperations()
|
|
'NAVD88 (ftUS)' to X, where we now consider the available transformations from 'NAVD88' to X that might exist in the database
|
|
functional change expected
|
|
transformations
|
|
https://bugs.chromium.org/p/oss-fuzz/issues/detail?id=18587
|
|
arbitrary number of steps (fixes #1632)
EPSG:9103 (NAD27 to ITRF2014 (1)) is now handled.
Note:EPSG:9104 (NAD27 to ITRF2014 (2)) is not currently, since it uses
for step EPSG:8861 (NAD83(HARN) to NAD83(FBN) (1))
an unsupported transformation method (NADCON5 (3D), EPSG:1075).
|
|
verticalCRS to a 2D CRS
|
|
Relates to https://github.com/OSGeo/gdal/issues/1856
|
|
When we had a transformation between a compoundCRS and a target geographicCRS,
we did not take into account that in the vertical->other_geog_CRS transformation
we used, the other_geog_CRS was an implicit interpolation CRS. Thus before
doing vertical adjustment, we must go to this interpolation CRS.
The workflow is thus:
source CRS -> interpolation CRS + vertical adjustment + interplation CRS -> target CRS
|