PROJ RFC 1: Project Committee Guidelines

+
+
Author
+

Frank Warmerdam, Howard Butler

+
+
Contact
+

howard@hobu.co

+
+
Status
+

Passed

+
+
Last Updated
+

2018-06-08

+
+
+
+

Summary

+

This document describes how the PROJ Project Steering Committee (PSC) +determines membership, and makes decisions on all aspects of the +PROJ project - both technical and non-technical.

+

Examples of PSC management responsibilities:

+
    +
  • setting the overall development road map

  • +
  • developing technical standards and policies (e.g. coding standards, +file naming conventions, etc…)

  • +
  • ensuring regular releases (major and maintenance) of PROJ software

  • +
  • reviewing RFC for technical enhancements to the software

  • +
  • project infrastructure (e.g. GitHub, continuous integration hosting options, etc…)

  • +
  • formalization of affiliation with external entities such as OSGeo

  • +
  • setting project priorities, especially with respect to project sponsorship

  • +
  • creation and oversight of specialized sub-committees (e.g. project +infrastructure, training)

  • +
+

In brief the project team votes on proposals on the proj mailing list. Proposals are available for review for at least two days, and a single +veto is sufficient delay progress though ultimately a majority of members can +pass a proposal.

+
+
+

List of PSC Members

+

(up-to-date as of 2018-06)

+ +
+
+

Detailed Process

+
    +
  • Proposals are written up and submitted on the proj mailing list +for discussion and voting, by any interested party, not just +committee members.

  • +
  • Proposals need to be available for review for at least two business +days before a final decision can be made.

  • +
  • Respondents may vote “+1” to indicate support for the proposal and a +willingness to support implementation.

  • +
  • Respondents may vote “-1” to veto a proposal, but must provide clear +reasoning and alternate approaches to resolving the problem within +the two days.

  • +
  • A vote of -0 indicates mild disagreement, but has no effect. A 0 +indicates no opinion. A +0 indicate mild support, but has no +effect.

  • +
  • Anyone may comment on proposals on the list, but only members of the +Project Steering Committee’s votes will be counted.

  • +
  • A proposal will be accepted if it receives +2 (including the +author) and no vetoes (-1).

  • +
  • If a proposal is vetoed, and it cannot be revised to satisfy all +parties, then it can be resubmitted for an override vote in which a +majority of all eligible voters indicating +1 is sufficient to pass it. +Note that this is a majority of all committee members, not just those who +actively vote.

  • +
  • Upon completion of discussion and voting the author should announce +whether they are proceeding (proposal accepted) or are withdrawing +their proposal (vetoed).

  • +
  • The Chair gets a vote.

  • +
  • The Chair is responsible for keeping track of who is a member of the +Project Steering Committee (perhaps as part of a PSC file in CVS).

  • +
  • Addition and removal of members from the committee, as well as selection +of a Chair should be handled as a proposal to the committee.

  • +
  • The Chair adjudicates in cases of disputes about voting.

  • +
+
+

RFC Origin

+

PROJ RFC and Project Steering Committee is derived from similar governance +bodies in both the GDAL and +MapServer software +projects.

+
+
+
+

When is Vote Required?

+
    +
  • Any change to committee membership (new members, removing inactive members)

  • +
  • Changes to project infrastructure (e.g. tool, location or substantive +configuration)

  • +
  • Anything that could cause backward compatibility issues.

  • +
  • Adding substantial amounts of new code.

  • +
  • Changing inter-subsystem APIs, or objects.

  • +
  • Issues of procedure.

  • +
  • When releases should take place.

  • +
  • Anything dealing with relationships with external entities such as OSGeo

  • +
  • Anything that might be controversial.

  • +
+
+
+

Observations

+
    +
  • The Chair is the ultimate adjudicator if things break down.

  • +
  • The absolute majority rule can be used to override an obstructionist +veto, but it is intended that in normal circumstances vetoers need to be +convinced to withdraw their veto. We are trying to reach consensus.

  • +
+
+
+

Committee Membership

+

The PSC is made up of individuals consisting of technical contributors +(e.g. developers) and prominent members of the PROJ user community. +There is no set number of members for the PSC although the initial desire +is to set the membership at 6.

+
+

Adding Members

+

Any member of the proj mailing list may nominate someone for +committee membership at any time. Only existing PSC committee members may +vote on new members. Nominees must receive a majority vote from existing +members to be added to the PSC.

+
+
+

Stepping Down

+

If for any reason a PSC member is not able to fully participate then they +certainly are free to step down. If a member is not active (e.g. no +voting, no IRC or email participation) for a period of two months then +the committee reserves the right to seek nominations to fill that position. +Should that person become active again (hey, it happens) then they would +certainly be welcome, but would require a nomination.

+
+
+
+

Membership Responsibilities

+
+

Guiding Development

+

Members should take an active role guiding the development of new features +they feel passionate about. Once a change request has been accepted +and given a green light to proceed does not mean the members are free of +their obligation. PSC members voting “+1” for a change request are +expected to stay engaged and ensure the change is implemented and +documented in a way that is most beneficial to users. Note that this +applies not only to change requests that affect code, but also those +that affect the web site, technical infrastructure, policies and standards.

+
+
+

Mailing List Participation

+

PSC members are expected to be active on the +proj mailing list, subject to Open Source mailing list +etiquette. Non-developer members of the PSC are not expected to respond +to coding level questions on the developer mailing list, however they +are expected to provide their thoughts and opinions on user level +requirements and compatibility issues when RFC discussions take place.

+
+
+
+

Updates

+

June 2018

+

RFC 1 was ratified by the following members

+
+
+ + +
+